Home/Portfolio/River North/500 W Superior St — River North Whole-Condo Remodel
Pink square tile shower on a white prefab pan behind a glass door, condo guest bathroom before remodel at The Montgomery, 500 W Superior St, River North Chicago
Green glazed vertical stack tile to the ceiling, a long recessed niche and a mosaic shower floor, condo guest bathroom after remodel at The Montgomery, 500 W Superior St, River North Chicago
BeforeAfter
⇄
◂ Drag anywhere on the photo ▸

River North condo remodel at The Montgomery: designed first, built one bathroom at a time

$120,820All-in · fixed price
May–Oct2 Baths, Glass Transom, 9 Doors

River North · 60654 · Completed October 2026 · page updated 2026-11-02

Portfolio · River North

500 W Superior St

High-rise condo, The Montgomery on Superior · Near North Side · 60654
Scope2 Baths, Glass Transom, 9 Doors
TimelineSigned May 2026, plans approved July 10, completed October 2026
Investment$120,820 all-in
PermitsBuilding approval July 10 · engineer's sealed letter · City permits where required
Warranty2-Year Workmanship
Guest bath rebuilt from the slab on sand-cement mud beds
Primary shower rebuilt, heated floor left untouched
Glass transom above the kitchen wall, engineer's sealed letter
Nine new doors, new oak, new lighting through the unit
Book a Consultation → (312) 544-9150
Chapter 1 · The Building

Why does The Montgomery need a different kind of contractor?

The Montgomery on Superior was built in 1972 as the Montgomery Ward headquarters, designed by Minoru Yamasaki, the architect of the World Trade Center, and converted to condominiums in 2005 and 2006. For Chicago condo remodeling it is one of the most interesting buildings around, and for River North condo remodeling it sets the bar, and the rules show it. Work runs 8 to 5, Monday through Saturday, by freight elevator only, with corridor protection, negative-air dust control and time-stamped corridor photos every day. Water shut-offs take written approval and 72 hours of notice. We carried the whole approval package, and the plans were approved on July 10, 2026.

Chapter 2 · The Guest Shower

From a prefab pan to green tile on a real mud bed

The guest bath had pink square tile and a white prefab pan. All of it came out, down to the slab, along with the floor and the prefab underlayment. The shower floor is now traditional sand-cement sloped a quarter inch per foot to the same drain, under a crack-isolation membrane and two coats of liquid waterproofing up the walls to the ceiling. Gabriella drew the soft green vertical stack at our Lincoln Park studio, and the finished room follows her drawing, down to the long niche.

BeforePink square wall tile and a white prefab shower pan behind a glass door in a condo guest bathroom
Before: pink tile, prefab pan.
DesignDesign rendering of a guest bathroom with green vertical shower tile, a long niche, a wood vanity with a white top and two alabaster sconces
Design: Gabriella's rendering, approved before anything was ordered.
AfterGreen glazed vertical stack shower tile to the ceiling with a long recessed niche and a small mosaic floor
After: tile to the ceiling, built from the drawing.
Chapter 3 · The Details

The niche, the valve and the light

The niche is framed, cement-boarded and waterproofed, then lined with the same mosaic as the shower floor, so the back of it reads as one piece with the floor. The shower head and valve trim are new, on a handheld. Inside the room, the bathroom floor has its own new mud bed about an inch and a quarter thick, with new large-format tile and new baseboards set after it cured.

AfterRecessed shower niche lined in small stone mosaic inside green glazed vertical tile with metal edge trim
After: the niche, lined in the floor mosaic.
AfterGreen glazed tile shower wall with a chrome handheld shower, valve trim and a long recessed niche
After: handheld, new valve trim.
Chapter 4 · The Guest Vanity

Black granite out, white quartz and alabaster in

The black granite and the wall-to-wall mirror with its single light bar came out. In their place is a new vanity with a white quartz top and an undermount sink, a rounded mirror, a new faucet on new shut-off valves, and a pair of alabaster-look sconces. The room also got a recessed shower light on a dimmer, a new code-vented recessed fan, a new toilet, a wallpaper accent wall and fresh paint.

BeforeWood vanity with a black granite top and a wide mirror under a single light bar beside a toilet, before remodel
Before: black granite, one light bar.
AfterWhite quartz vanity top with an undermount sink, a rounded black frame mirror and two alabaster-look wall sconces
After: quartz, a rounded mirror, two sconces.
Chapter 5 · The Primary Shower

Only the shower came out, and the heated floor never noticed

The primary bath had good bones: a hex marble floor over a working heated floor, a long double vanity with a stone top, double sinks and a tub. All of that stayed, covered and protected, and the heated floor was checked again at the end. The work stayed inside the shower enclosure. The prefab pan and the wall tile came out, then a new mud bed went in on the existing drain, with membrane, waterproofing and cement board. Large-format gray tile now runs to the ceiling over a small mosaic floor.

BeforeWhite subway wall tile with two vertical mosaic strips and a white prefab shower pan behind a glass door, before remodel
Before: mosaic strips, prefab pan.
DesignDesign rendering of a walk-in shower with large gray tile, a long recessed niche and a small mosaic floor
Design: large-format gray, a long niche.
AfterLarge-format gray stone-look shower walls to the ceiling with a recessed niche, a small white mosaic floor and a square drain
After: large-format walls, mosaic floor, square drain.
Chapter 6 · The Tub Wall

Same tub, a new wall behind it

The contract gave three options for the wall above the tub: paint, tile or wallpaper, all at the same price. At the studio the choice was a band of fluted vertical tile at the height of the old mosaic strip, with clean paint above. The tub stayed. A new tub light, an overhead recessed light and new sconces at both vanity stations all went on dimmers. Both stations also got new mirrors, faucets and sink hardware, and the vanity run got new painted toe kicks.

BeforeWhite tub surround with a thin mosaic tile strip along the wall and a hex marble floor, before remodel
Before: a thin mosaic strip.
DesignDesign rendering of a white tub with a band of fluted gray vertical tile on the wall above it and a brushed nickel faucet
Design: a fluted band, soft gray.
AfterWhite tub with a band of fluted gray vertical tile on two walls and the original hex marble floor kept in place
After: the band built, the hex floor kept.
Chapter 7 · The Kitchen

We did not remodel this kitchen. We changed what it needed.

The solid-wood cabinets and the stone counter stayed, because they were good. What changed: a white vertical stack backsplash over a repaired wall, a new undermount sink and faucet, and under-cabinet LEDs on a dimmer. The sink was the careful part, because the old one was bonded to the stone: heat to soften the adhesive, cut the bond, drop the clips, inspect the cutout, then set the new one. The wall above the kitchen came out too, for the glass transom in the next chapter.

DesignDesign rendering of a wood kitchen with a white vertical stack tile backsplash, under-cabinet lighting, a pull-down faucet and an undermount steel sink
Design: the backsplash and the lighting, drawn first.
AfterWhite glossy vertical stack tile backsplash under wood cabinets behind a stainless gas range and an over-the-range microwave
After: the backsplash, with the owners' appliances set and connected.
Chapter 8 · The Transom and the Whole Unit

The wall came out above the kitchen, and glass went in

We removed the top of the wall between the kitchen and the guest bedroom and framed it with a proper header. A custom multi-panel coated tempered-glass transom now lets light through while the wall keeps its privacy and sound. That is the item the building treats most seriously, so it went in with a structural engineer's sealed letter and acoustical sealing to the building's rules. Around it: nine new doors, solid white oak in the guest bedroom stained on site to match the hallway, a new cluster of recessed cans in the living room, new entry and dining fixtures, four recessed lights in the primary closet and new code smoke and CO detectors.

AfterBlack drum ceiling fixture with a wood cross detail and a glowing diffuser hung from a painted condo ceiling beside a recessed light
After: the owners' statement fixture, on a new dimmer.
Investment · 500 W Superior St

What did this whole-condo remodel at The Montgomery cost?

Two bathrooms, a glass transom, a kitchen update, nine doors and lighting through the unit, on one fixed-price contract:

$120,820
All-In · Whole Condo · May–Oct

The figure is the signed contract at $116,750, plus $6,320 of electrical, plumbing and painting added during the job, less $2,250 in credits. The contract carried a $29,000 materials allowance, and the appliances were the owners' own. Our Chicago condo remodeling cost guide puts a full condo renovation at $60,000 to $150,000 or more.

Building fees are separate and go straight to the association. At The Montgomery that includes water shut-offs, with a $300 minimum per drain or riser in the building's rules ($350 quoted on this job), and freight elevator time, at $200 per two hours.
Complete Scope of Work

What was in the signed scope, room by room?

Consolidated from the signed contract, the design selections and the final walkthrough. Two contract items were removed before the work was done, a 220V range circuit and a counter buff and polish, and both were credited.

Kitchen Update, Cabinets and Stone Kept

  • Solid-wood cabinets cleaned, hinges adjusted; stone counter kept
  • Bonded sink removed, new undermount sink set in the existing cutout, new clips and silicone, pressure-tested
  • New pull-down faucet; owner-furnished disposal installed with dishwasher tie-in and air gap or high loop per code
  • New white ceramic vertical stack backsplash, with the wall behind the counter repaired first
  • Four island pendants replaced with recessed cans; under-cabinet LED on a dimmer
  • New painted-wood toe kicks; refrigerator water line and owner-furnished appliances received, set and connected

Guest Bathroom, Full Rebuild

  • Vanity, counter, mirror, toilet, light, fan, floor tile, prefab underlayment, prefab pan and wall tile all removed to the slab; drain location kept
  • Sand-cement mud beds at the bathroom floor (about 1.25 in) and the shower floor (1/4 in per foot, TCNA B415); crack-isolation membrane
  • Cement board on shower walls; liquid waterproofing to the ceiling, shower floor and niche, two coats minimum
  • One recessed niche; new tile on shower walls to ceiling, shower floor and bathroom floor
  • New vanity, quartz top, undermount sink, faucet, shut-off valves, mirror, toilet, shower head and valve trim
  • Vanity lighting, recessed shower light on a dimmer, new code-vented recessed fan
  • Wallpaper accent wall, new baseboards, towel bar and paper holder, paint

Primary Bathroom, Shower Rebuild

  • Kept and protected: hex floor tile, heated floor, vanity cabinet, stone top, double sinks and tub; heated floor checked at the end
  • Inside the shower only: prefab pan and wall tile out, new sloped mud bed on the existing drain, membrane, waterproofing, cement board
  • New tile to ceiling, new floor tile, one recessed niche, new shower head and mixing valve
  • Tub wall finished per the design election: a fluted tile band and paint
  • New mirrors, faucets and sink hardware at both vanity stations, two sconces, overhead recessed light and tub light on dimmers
  • New toilet, new code-vented recessed fan, new painted toe kicks at the vanity run, wallpaper accent, paint

Nine Doors

  • Solid-core flush swing doors: guest bedroom, guest bath, primary bedroom, primary bath, primary linen closet
  • Louvered laundry door; two pantry doors as a side-by-side swing pair, not a bifold
  • New sliding door and track at the primary walk-in closet
  • New hinges, strike plates, stops and levers; two finish coats on site
  • Primary-bath linen door and guest-bedroom closet doors kept and paint-matched

Flooring, Living Room and Lighting

  • Guest bedroom carpet, pad and tack strips out; subfloor prepped; 3/4 in solid white oak, sanded and stained on site to match the hallway, flush at the door
  • Guest closet doors trimmed for the new floor height, track repaired
  • Living room drywall patched from the old wall unit, painted, new cluster of recessed cans
  • New entry ceiling fixture; owner-furnished dining fixture installed; four recessed lights in the primary closet
  • New switches, faceplates and dimmers through the unit; all smoke and CO detectors replaced with current Chicago-code units

Glass Transom

  • Top of the guest bedroom and kitchen wall opened and framed with header and lintel
  • Custom multi-panel coated tempered glass, field-measured, delivered by freight slot and installed
  • Acoustical sealing at the perimeter, drywall returns on both faces
  • Drywall repair at the transom and the adjoining primary bath wall, skimmed and painted
  • Structural engineer's sealed letter commissioned and paid for by us; City permit work where required

Licensed Trades

  • Licensed Chicago electrician: recessed cans, dimmers, fan circuits, detectors, appliance connections, under City permit where required
  • Licensed Chicago plumber: kitchen sink, faucet and disposal, two shower heads and valves, two toilets, all vanity faucets, shut-offs and stops; no fixtures relocated
  • Stone partner: bonded sink removal, guest bath quartz fabrication and install
  • Custom glass subcontractor: transom

The Building, Handled

  • Full approval package: construction documents, engineer's letter, insurance certificates worded to the building's rules, trade licenses, schedule, renderings and product data sheets
  • Plans approved July 10, 2026
  • Water shut-offs scheduled through management and the building engineer, each with written approval and 72 hours of notice
  • Corridor protection, daily check-in and badges, time-stamped corridor photos, negative-air dust control, freight-slot debris removal
  • One bathroom at a time so the owners always had a working bath; final deep clean; 2-year workmanship warranty
500+Chicago projects since 2013
A+BBB rated
300+condo buildings worked in
$2Mliability · IL #TGC098779
4.9★on Google
Common Questions

Remodeling a condo at The Montgomery, answered

What did this whole-condo remodel at The Montgomery cost?

This remodel at 500 W Superior St came to $120,820 all-in: a $116,750 fixed contract, $6,320 of work added during the job and $2,250 in credits. It covered two bathrooms, a glass transom, a kitchen update without new cabinets or counters, nine doors and lighting through the unit. Our condo cost guide puts full Chicago condo renovations at $60,000 to $150,000 or more.

What does The Montgomery on Superior require before a remodel starts?

Construction documents, insurance certificates worded to the building's own rules, trade licenses, a schedule and a shut-down plan, plus a structural engineer's sealed letter for any wall opening. Work runs 8 to 5, Monday through Saturday, by freight elevator. We prepare the package ourselves, and on this job the plans were approved on July 10, 2026. See our high-rise condo remodeling page.

Can you add a glass transom to a wall at The Montgomery?

Yes, and we did on this job. The top of the wall between the guest bedroom and the kitchen was opened and framed with a header, then fitted with custom multi-panel coated tempered glass and sealed for sound. The building treats it as a structural item, so it needed an engineer's sealed letter and permit work with the City. Light moves between the rooms and the wall still does its job.

How do water shut-offs work at 500 W Superior?

A shut-off needs written approval from management and at least 72 hours of notice, and each request states the expected downtime. The building's own engineer drains and recharges the risers. The building's rules set a $300 minimum per drain or riser, paid by the owner, and our second shut-off on this job was quoted at $350. Your insurance certificate and your plumber's license must be accepted first, or the date is lost.

Can a shower be rebuilt without touching a heated bathroom floor?

Yes. In this primary bath the hex marble floor and the heated system under it were never disturbed. All new mud bed, waterproofing and tile stayed inside the shower enclosure, so the prefab pan could come out while the floor outside stayed covered and protected. The heated floor was checked again at the end. It kept the good parts of the room and spent the money where the problem was.

Can two units at The Montgomery on Superior be combined?

The Montgomery is among the Chicago towers known to permit combinations, but the board still has to approve an alteration agreement, so read the declaration and bylaws before buying a second unit. Our condo combination guide covers how those approvals work. Send us your floor plan and we will tell you what the rules allow. More on River North condo remodeling.

Start Your Project

Own at The Montgomery or anywhere in River North?

You have seen how a job goes in this building, from the 700 N Larrabee bathrooms and the River North kitchen under $50K to this one. Start with a private consultation at your home, at our Lincoln Park design studio, or online. We handle the building package, draw every room before anything is ordered, and hold a fixed price.

Book a Consultation → Call (312) 544-9150
Assembly Squad Remodeling, LLC · Illinois GC License #TGC098779 · EPA Lead-Safe Certified · A+ BBB · Rated 4.9★ on Google · 500+ projects since 2013
500 W Superior St · River North · Chicago, IL 60654 · (312) 544-9150 · Condo remodeling Chicago
Assembly Squad
Remodeling

Chicago's boutique design-build remodeling company since 2013. Kitchen, bathroom, condo, basement, and whole-home renovations across Chicago and the North Shore.

IL #TGC098779
A+ BBB
NARI Chicago
NKBA Member
EPA Lead-Safe
$2M Insured
★ 4.9 on Google · Read our reviews

Services

  • Kitchen Remodeling
  • Bathroom Remodeling
  • Condo Remodeling
  • Basement Remodeling
  • Whole House Remodeling
  • Attic Conversions
  • Custom Cabinets
  • Design-Build Studio

Explore

  • About Us
  • All Services
  • Project Portfolio
  • Service Areas
  • Kitchen Remodel Cost
  • North Shore
  • Blog
  • Contact Us

Contact

Phone(312) 544-9150
Headquarters205 N Michigan Ave, Suite 810
Chicago, IL 60601
Lincoln Park Studio2315 N Southport Ave
Chicago, IL 60614

Mon–Fri 9–6 · Sat 10–4

Chicago Neighborhoods

Lincoln Park · Gold Coast · River North · Lakeview · Wicker Park · West Loop · Bucktown · Logan Square · + more →

North Shore

Winnetka · Lake Forest · Highland Park · Evanston · Wilmette · Northbrook
Assembly Squad Remodeling LLC · All Rights Reserved ©2013–2026 · IL License #TGC098779 · A+ BBB · NARI Chicago
Privacy Policy Get a Free Estimate
  • Home
  • About Us
  • Services
  • GET FREE ESTIMATE
  • Portfolio
  • Service Area
  • Blog